National Assembly Complex.
He disclosed this on Thursday during an oversight tour of some projects
in the capital city by the Senate Committee on FCT.
The minister while noting that the National Assembly Phase II popularly
known as “the White House” was realised from 1996 to 1999 by ITB Nigeria
Ltd added that no major rehabilitation works had been carried out on the
building over the years.
He said that the contract which was awarded on Dec. 30, 2021 for 16
months has a contract sum of N30, 229, 290, 830.35 while the amount paid
was N 9, 200, 000, 000.
“The commencement date is April 16 and is expected to be completed Aug.
15, 2023.
The minister listed other priority projects embarked upon by the
administration to include rehabilitation of Federal Secretariat complex,
construction of southern park way from Christian Center to ring road.
Others he said were the rehabilitation of expansion of Outer Southern
Expressway, provision of engineering infrastructure for Wuye District,
rehabilitation and expansion of Outer Southern Expressway Villa
Roundabout and completion of B6, B12 and Circle Road in Central Area.
He explained that the ministry gave some projects in the city priority
over others due to scarcity of funds.
“What we did was because of the scarcity of funds, we prioritised key
infrastructure projects to get them completed.
“And in deciding to the ones that fit into that category, we looked at
the ones that will give the maximum benefit to the maximum number of
people.
“All the four projects we visited, you find that they are all road
projects that are meant to link one section of the Abuja city to another
and that is the whole idea.
“The masterplan has been designed in such a way that they complement
each other.
“So if you finish one portion and you don’t do the other one, then you
don’t get the full utility of that particular road.”
Bello further said that it was the intention of the ministry that as the
tenure of President Muhammadu Buhari’s administration rounds off, a
number of projects would be completed.
“Some of them we intend to develop them to a level whereby the next team
should be able to do it.
“Ultimately, the objective is to make Abuja a vibrant city; a city where
people will feel comfortable; where there wouldn’t be traffic gridlock
and where facilities will work.”
He said that working together with the Senate, the ministry would be
able to achieve the completion of the projects.
Bello, however, said that running a mega city was a huge challenge
noting that demographically, Abuja had changed tremendously.
“So the main challenge is to be able to fast tract the provision of
infrastructure at a pace that will be able to match with population
growth.”
Also speaking, Chairman Senate Committee on FCT Sen. Tolu Odebiyi, who
led the committee members said:”what we have seen is quite impressive.
“We believe that in the twilight of this administration, in the next
month, it is important we catalogue all the projects that are being done
and prioritise the ones that must be completed before the end of this
term.
“This is so that we can also make sure we provide the adequate funding
and budget for it.
“Their budget is going to be forwarded to us very shortly and it is
important we come and see the state of the work and the completion rate
of the programme before we take them on.
“Like any other project, we will make sure all the projects that require
priority are given the due attention like any other project.”(NAN)